Huddersfield rail tunnel improvements
Preparing for electrification: innovative tunnel strengthening delivers safer, more efficient rail upgrades
The TransPennine Route Upgrade (TRU) is a multi-billion-pound programme of railway improvements that will deliver faster, greener and more reliable journeys between Manchester, Huddersfield, Leeds and York.
As part of this programme, four tunnels – Huddersfield North, Huddersfield South, Gledholt North and Gledholt South – needed to be strengthened with brick linings, to support new overhead line equipment.
But this represented a major geotechnical challenge. The work had to be carried out within highly restricted possession windows – sometimes as short as three hours – while complying fully with Network Rail standards. Also, using the originally specified grout proved impractical, as it required installation methods that would expose workers to significant hand-arm vibration and increase the time they needed to spend in hazardous environments.
Working in confined, high-risk environments, the BAM ground engineering team took a safety-first approach, focusing on three core risks: hand-arm vibration syndrome, manual handling and reducing time spent in hazardous rail possessions. These priorities shaped a series of innovations that transformed both the methodology and safety performance of the works.
BAM is playing a key role in TRU, providing infrastructure and specialist ground engineering services as part of the £2bn TRUWest Alliance contract.
On this particular element of the project – thanks to close collaboration with the designer, client and key supply chain partners – the ground engineering team developed a robust and technically effective solution that not only met Network Rail requirements, but also improved safety, simplified installation and supported the overall programme delivery.
Project details
- Client
Network Rail - Ground engineering prime contractor
BAM - Designer
COWI - Specialist resin suppliers/contractors
CK-Tech/Master Builders Construction Chemicals
historic tunnels, some dating back to the mid 1800s
person hours of manual drilling eliminated
resin-based grout solution
angle finders used to remotely verify mast angles from ground level
The challenge: ensuring safety and performance in tight possession windows
Electrifying the TransPennine route involves installing overhead power lines above all the tracks. But in the hilly terrain of northern England, many of these tracks pass through tunnels originally designed and built by the Victorians. The solution is to retrofit them with a new brick lining that’s strong enough to support the new cables.
However, complying with Network Rail standards on the Huddersfield Tunnels upgrade would have involved extensive manual drilling (around 3,000 individual 16–25mm holes) before grout could be injected: representing a significant vibration risk for operatives using hand‑held rotary hammer drills.
The cementitious grouts specified in Network Rail standards were also unsuitable, as they would take too long to cure given the tight time constraints imposed by Huddersfield Station’s operational schedule.
Using alternative, resin-based grouts would not necessarily solve the issue, as these products are quite niche which could introduce uncertainty around delivery and the availability of specialist resources to install them.
The extremely short working windows available to BAM on this project also added real pressure. The mismatch between material performance and site conditions posed a serious risk to programme delivery and the overall success of the project.
The BAM solution: a pragmatic and collaborative approach
BAM’s approach was driven by close and proactive collaborations with the client, designer and supply chain partners to deliver a robust geotechnical solution, tailored to address the specific technical and operational challenges of the project.
For example, BAM worked closely with the designer to mitigate vibration risks during borehole construction by developing alternative drilling techniques and parameters.
Traditional Network Rail tunnel lining repairs involve drilling 16–25mm holes using hand‑held rotary hammer drills, before injecting grout. Thousands of holes were needed for this project: which would have meant hundreds of hours of exposure to vibration risks for operatives using conventional methods. In agreement with the designer, increasing hole diameters to 35mm and using mechanical methods meant that workers were kept away from drilling activity.
And for the grouting phase, BAM proposed substitute materials that met specification requirements while demonstrating proven effectiveness in comparable environments.
Instead of the traditional cement-type grouts usually specified for these kinds of Network Rail installations, BAM turned to a resin-based water management solution. This kind of grout is typically installed by specialist suppliers, which could have involved bringing unnecessary personnel into the high-risk tunnel.
BAM partnered with trusted supply chain specialists to identify and implement the most appropriate products. Ultimately the team chose a single resin grout capable of fulfilling all three specified functions on the project: filling fractures, managing water ingress and ‘stitch and pinning’ brickwork.
Working closely together, BAM and its specialist suppliers jointly developed an intensive eight-week training programme, backed up by on-site support during initial deployment. This enabled BAM to deliver the grouting solution itself, rather than bringing in external contractors.
Using mechanised drilling methods – with lightweight aluminium drill masts mounted on road-rail vehicles and remote-controlled high-frequency drill motors – not only eliminated hand-held drilling completely but also protected the existing fragile brickwork and reduced the need for subsequent rework.
This innovative approach not only met Network Rail’s technical requirements but also streamlined operations significantly.
The result: new ways to minimise risk and improve performance
Up-front engagement, innovation and continuous collaboration ensured safety on this project without compromising design intent.
By consolidating the grouting process into a single material, BAM was able to eliminate the complexity and inefficiencies associated with managing multiple grout types.
This simplification delivered several operational advantages. Repeatability of process, familiarity with equipment and a single-source supply chain allowed the team to focus on refining techniques and improving productivity. It also enhanced quality assurance and reduced the risk of logistical delays, contributing to greater programme certainty.
The innovations produced measurable and significant safety improvements. The combination of design changes, mechanising the drilling process and using trained BAM team members to instal the grouting eliminated over 3,000 person‑hours of exposure to high‑risk vibration‑related activities.
This not only improved safety outcomes but also demonstrated BAM’s commitment to innovation and workforce wellbeing. Together, these solutions delivered a more efficient, safer and technically robust outcome under highly constrained site conditions.
The project has already contributed to wider industry improvements around the use of resin in future tunnel repairs and upgrades.
The BAM team scooped the Geotechnical Solutions Award at the 2025 Federation of Piling Specialists (FPS) Awards and was shortlisted in the Safety Innovation category. At the 2026 Ground Engineering Awards, the project won the Health and Safety category.
“The result [of BAM’s approach] has been measurable improvement in safety outcomes alongside meaningful financial efficiency gains – an outcome the judges found both credible and impressive.”
GE Awards 2026 judges’ comments