Batts Combe Quarry, Somerset

A complex blast design to access untapped limestone resources

Batts Combe Quarry, near Cheddar in Somerset, is a historic limestone quarry producing aggregates that are used in road maintenance, industry and construction. It’s one of the main suppliers for the Hinkley Point C power station, currently being built nearby.

The quarry has been processing limestone for over a century. As far back as the 1920s, lime kilns and associated plant were commissioned and built. But in 2012, the main lime kiln was decommissioned as UK steel production declined.

The kiln was located on top of around 35,000 tonnes of unrecovered aggregate reserves, which the quarry operators – Heidelberg Materials UK – had left untouched since the kiln was removed. They’d been told that it would be impossible to extract the valuable rock without potentially causing damage to the nearby fixed plant in that location of the quarry. 

The area to be excavated also presented several geotechnical challenges.

Heidelberg Materials UK turned to its drill and blast partner, BAM, to design and execute a blast plan that would allow access to this important resource. The blast required to be designed using a specialist initiation system, be predictably safe, effective and sustainable in line with the client’s development, community and environmental priorities.

Project details

  • Client
    Heidelberg Materials UK
  • Drill and blast partner
    BAM
Icon tonnes
35000

Tonnes of limestone potentially available

icon Clock
1890

Quarrying operations began at Batts Combe

Icon measurement
22 metre

clearance from vital on-site plant

The challenge: no second chance on a complex site

As well as accessing the aggregate in this difficult location, the quarry needed to establish a new stocking area for a large-scale project while minimizing traffic movements around the plant area and maximising loading times and efficiencies.

The location of the old kiln was ideally situated and would provide the perfect solution. But could it be done safely and without damage to the plant?

At the nearest point, the fixed plant was just 22 meters away from the 11m rock face.

This challenging blast also had to be completed within the local planning constraints around noise and vibration.

The BAM solution: predictability, safety and efficiency

The drill and blast team from BAM ground engineering work with Heidelberg Materials across the UK.

The BAM team created a complex blast design for Batts Combe, designed to ensure that its drill and blast specialist team could complete the work safely and effectively. 
The initial pre-drill survey had highlighted some reinforced steel bars that remained in place after the plant had been removed. Therefore, the process started with the quarry staff removing these.

BAM was then able to complete a full site survey and design the blast focused on three key factors: safety, blast performance and adhering to the quarry development plan and geotechnical assessment design for the quarry.

The chosen blast pattern involved the drill holes being mark on 4 metre by 4 metre pattern. The perimeter of the blast was marked with a line of holes at 3 metre spacings which would be lightly charged to create a “smooth blast” effect on the final face and stabilise it in line with the geotechnical assessment. BAM used an electronic initiation system to ensure accurate timings, good fragmentation and vibration control.

Explosives were positioned so that the energy was distributed and concentrated efficiency and effectively. The holes were initiated at two points on separate timings. That reduced the maximum instantaneous charge without compromising the fragmentation of the rock.

The blast initiation plan used burden relief software and ensured that the blast pile was thrown away from the point closest to the plant.

Reducing charge weights also helped to reduce throw and minimise vibration caused by the blast.

Post-blast

The result: a textbook blast with no need for remediation

The blast was fired safely and delivered exceptional results. Fragmentation was even better than the client’s expectations, there was no damage to the adjacent plant and vibration levels were extremely low, not exceeding the planning limit for the site.

Once the blast pile had been excavated, the final face proved to be excellent and no further remedial works – such as geo-netting or rock bolts – was needed to stabilise it. This significantly reduced the programme of works, keeping costs to the minimum.

“Given the unique parameters and additional attention to detail required, we couldn’t be happier with the outcome! The BAM team delivered exceptional results that have positively impacted our operations.” 

Kyle Boyd Production Supervisor, Batts Combe Quarry, Heidelberg Materials UK